1958 - N&W Completes Setting Of Piles For Underpass
    NW Mailing List 
    nw-mailing-list at nwhs.org
       
    Sun Jul 27 22:13:36 EDT 2008
    
    
  
Roanoke Times - July 27, 1958
N&W Completes Setting Of Piles For Underpass
   The Norfolk and Western Railway has completed the setting of piles 
for the first stage of construction of the underpass of the 
Shenandoah Division tracks connecting Liberty and Mundy roads, NE.
   The piles still must be cut down to grade to permit placing of 
bridge timbers to support the southbound tracks and a siding while 
the contractor is building the box on the east side.
   About 75 per cent of the piles have been set and the remainder, 
which will support the northbound tracks, will be driven when the 
first half of the box is complete.
   All the preliminary work to be done by the N&W will be complete 
when the contractor moves in.
   City Council tomorrow is expected to award the contract to Ralph 
E. Mills Co., at a figure of $161,180.
   When bids were opened tow weeks ago, Council indicated its 
intention to accept the bid. It was on the strength of this implied 
acceptance that the N&W has gone ahead with the work in order that 
there would be little or no delay when the contractor goes on the site.
   Mills was low bidder on both phases of the work - the underpass 
itself and the laying of sanitary and storm sewers and paving of the 
connecting link.
   The work will require five or six months to complete.
-----------------------------------
- Ron Davis, Roger Link
-------------- next part --------------
A non-text attachment was scrubbed...
Name: 19580727.jpg
Type: application/octet-stream
Size: 24764 bytes
Desc: not available
Url : <http://six.pairlist.net/pipermail/nw-mailing-list/attachments/20080727/752d2b48/attachment-0001.obj>
    
    
More information about the NW-Mailing-List
mailing list