[StBernard] Katrina Permit & Electrical Permit--Craig

Westley Annis westley at da-parish.com
Wed Aug 23 22:14:53 EDT 2006


Donna,

The electrical permit will work and the extension is noted by the community
development office when it is due to the electrician. The Katrina permit is
fine, but has not been completed yet based on some additional requirements
that FEMA has placed on us. You can certainly get the electrical and then
double up on the other when it is ready.

Thanks for your kind words.

Good luck and God Bless,
Craig


-----Original Message-----
Craig,
I have read that an Electrical Permit is only good for 6 months and then you
have to file for an extension. My question is, would it be better to file
for a Katrina Permit, and is there a time frame for this permit?

Thank you so much. I appreciate you taking time to answer questions for all
who subscribe to this site. You have given us much needed knowledge, that
is not obtainable anywhere else. We all know you are a busy man and still
find time to help answer questions. Westley, these words are for you also.
Your site has helped many people and we thank you.
Donna F.