22,
no, the implementation period is 60 days after the adoption on April 3. And
if you or the previous owner has a permit on file to rebuild or a utility
permit then that counts as having started the process.
God Bless,
Craig
-----Original Message-----
I'm buying a house on Palmisano Blvd that was build in 1995. The act of
sale is not until April 16. Will I have to raise it to comply with FEMA's
new guidelines?